For personal use only

ASX ANNOUNCEMENT

18 March 2022

Review Complete on Significant Copper-Gold

Surface Material at Horseshoe Lights

  • In light of current favourable copper and gold pricing Horseshoe is actively assessing the potential future viability and commercialisation of extensive copper and gold surface materials at the Horseshoe Lights Project in WA
  • Horseshoe Lights Copper-Gold Project summary:
    1. Current in situ resource 128,000 t Cu metal @ 1.0% (0.5% cut-off)o Current M15 stockpile resource 2650 t Cu metal @ 1.1%
      o Current Flotation tailings resource 6,800 t Cu metal @ 0.48% and 15,300oz Au at 0.34 g/t
      o Extensive drilling (over 120km total) and metallurgical test work
      o Open pit only drilled to a depth of ~250m - proximal major deposits in Bryah Basin have been drilled to ~800-1000m
      o Horseshoe are targeting a Deep sulphide copper target - "Below the
      Dolerite" (BTD)
  • Surface Material Re-Treatment (SMART) project initiated in 2015 to assess potential for copper and gold recovery from flotation tailings
  • Oxide Cu-Au targets include M15 and C20 and subgrade stockpiles plus the North and South Waste Dumps
  • Sulphide copper targets include flotation tailings and North West Dump low grade copper stockpile
  • CIP Gold tailings require further testing for coarse gold recovery
  • Discussions underway regarding possible off-site treatment of remnant gold-only stockpiles and vat leach material
  • Entech engaged to update 2014 Scoping Study in light of current significantly higher copper prices
  • Evaluation of surface material opportunities to complement Horseshoe's plans to target main orebody extensions with deeper drilling, including the conceptual BTD target

_______________________________________________________________________

Horseshoe Metals Limited (ASX: HOR) (the 'Company') is pleased to provide the results of an initial review of the significant surface materials including tailings, stockpiles and dumps at its Horseshoe Lights Copper-Gold Project.

The Horseshoe Lights Copper-Gold Project is the original Cu/Au VMS discovery in the Bryah Basin and is located approx. 60 km west of DeGrussa Copper Mine operated by Sandfire Resources (ASX: SFR). Past production from Horseshoe Lights includes around 316,000 oz Au & 55 kt Cu metal in two phases of mining, and the deposit contains a current in situ resource 128 kt Cu metal @ 1.0% (0.5% cut-off)and 36,000 oz Au (refer Table 2).

The surface materials have been broadly grouped as follows (Figure 1):

Copper - Gold

Flotation tailings, Vat 2, M15/C20 Stockpiles and North Dump

Copper

Low-grade sulphide, subgrade, rehandle and South Dump

only

Gold tailings, leach vats, low grade, rehandle and ROM stockpiles

Gold

Results of Phase 1 testing of gold vat, gold re-handle and C20 stockpiles was reported in ASX releases dated 10 September and 26 November 2021.

Copper-Gold Materials Discussion

Flotation tailings - SMART Project

useThe flotation tailings comprise an inferred resource of 1.42 Mt at 0.48% Cu, 0.34g/t Au and 6.5g/t Ag for 6,800t Cu, 15,300oz Au and 295,000oz Ag (Table 2). Metallurgical test work completed in 2015 (see ASX releases dated 7 April and 21 May 2015) successfully confirmed that wet table concentrates up to 6% Cu could be produced. Further detailed metallurgical test work is planned to determine the optimal low-cost gravity recovery process required to produce saleable Cu-Au-Ag concentrates from reprocessing of the tailings material.

M15 Stockpiles

personalM15 stockpiles comprise an inferred resource of 243,000t at 1.1% Cu, 0.17g/t Au and 4.7g/t Ag for 2650t Cu, 1,300oz Au and 37,000oz Ag (Figure 1 and Table 2). Historical leaching test work (see ASX release dated 20 August

2015) demonstrated that oxide copper material is very amenable to acid leaching with copper recoveries up to 80% achieved. The M15 stockpiles are predominantly oxide copper and will be assessed as part of a metallurgical study aimed at assessing all surface oxide material including C20 stockpile (C20), North Waste Dump (NWD), Southern Waste Dump (SWD) and Copper Re-handle Stockpile (CRS).

C20 Stockpile

The C20 stockpile is understood to be a low grade rehandle stockpile created during the gold only CIP operations phase in the mid to late 1980's. During the subsequent 'Chalcocite' DSO mining phase, the surface of this stockpile was used a resample area for high grade ore excavated from the margins of the DSO orebody that may have been diluted during mining.

C20 stockpile contains significant oxide gold and copper mineralisation, significant recent drilling results (Figure

6, and Table 1) include:

9m

@ 1.69g/t Au and 0.4 % Cu from 1m in hole C20_RC8

For

6m

@ 1.20g/t Au from surface in hole C20_RC21

3m

@ 2.54g/t Au and 0.73% Cu from surface in hole C20_RC46

North Waste Dump

The North Waste Dump (NWD) was created during the early CIP gold production phase of the project during the mid to late 1980's and it is apparent any low grade oxide copper mineralisation mined adjacent to the gold-only mineralisation was deposited in the NWD.

There has been wide-spaced sampling of the dump by Reverse Circulation (RC) drilling as part of historic programmes targeted at bedrock mineralisation below the dump. A number of significant results were obtained during this phase (refer Figures 2 & 3, and Table 1) including:

13m @ 1.15% Cu from surface in hole RC878

only

12m @ 1.03% Cu from surface in hole RC883

6m @ 0.88% Cu from 6m in hole RC1083

I

fill drilling of the NWD is planned to allow assessment for inclusion in resource estimations.

Copper Materials Discussion

Low Grade Sulphide Stockpile (North West Dump)

use

Low grade copper sulphide material was deposited in a stockpile located on the top of the North West Waste

Dump (Figures 1 and 2) during the latter stages of mining the open pit in the early 1990's. This material appears

to be around 4-5 metres in thickness and has only been tested by 3 drill holes with a best result of 4m @ 1.16%

Cu from surface in WRL11 (see ASX release dated 12 September 2018). Further RC drilling is required to allow

completion of a resource estimate for this stockpile.

Subgrade, Re-handle Stockpiles and Southern Waste Dump

personalstockpile remains untested. RC drilling of these stockpiles is required to allow resource estimation. Results from

These stockpiles (Figures 1 and 4) were created during the Direct Ship Ore (DSO) phase of mining in the upper parts of the Cu orebody during the late 1980, and early 1990's. During the 'Chalcocite' DSO mining phase, these stockpile and re-handle areas were likely used as resample areas for high grade ore excavated from the margins of the DSO orebody that may have been diluted during mining. The Southern Waste Dump (SWD) appears to comprise low grade Cu oxide and Cu mineralised wasted mined from the mineralised halo adjacent to the high- grade Cu mineralisation. These stockpiles and the Southern Waste Dump have not been adequately tested and require auger and/or RC drilling to allow further assessment.

Gold Materials Discussion

Gold Stockpiles

Stockpiles A, B, C and the ROM stockpile were created during the CIP gold mining phase of operations in the mid to late 1980's. Historic drilling is limited to one hole in each of the stockpiles (Figure 4) whilst the ROM gold

the three holes include:

For

6m

@ 0.73g/t Au from 2m in hole WRL09

5m

@ 1.89g/t Au from 1m in hole WRL05

5m

@ 0.52g/t Au from surface in hole WRL03

Gold Leach Vats

Vat leach gold bearing material from early 1980's open pit mining activities prior to Barrack mines open pit and CIP gold operations during the mid to late 1980's has been auger drill tested (see ASX releases dated 6 August, 10 September and 26 November 2021). Material in Vats 3,4,5 and 6 averages 0.57 g/t Au whilst Vat 2 contains Cu- Au sulphide tailings and Vat 1 requires further assessment, having been substantially excavated (Figure 5).

Gold Re-Handle Stockpile

The area to the west of the Gold Vat area, now renamed the Gold Rehandle stockpile, consistently returned significant gold values averaging 1.13 g/t Au over a coherent mineable volume, increasing in depth from the west to the east, where it achieves a maximum height of 4m, in the vicinity of two now-covered (smaller) original gold

onlyleach Vats (referred to previously by the Company as Vats 7 and 8 - see ASX release dated 26 November 2021 and Figures 1 and 5).

Gold Tailings

The gold tailings require further sampling and assessment to determine the amount of coarse gravity recoverable gold still contained within this material, which has not been formally assessed for gold grade on an appropriate scale. The gold tailings also have small stockpiles of copper-mineralised material dumped on the surface of the landform which require further assessment.

useDiscussions are underway regarding potential offsite treatment of gold stockpiles remaining from the gold mining activities in the 1980's. Further evaluation of these stockpiles may be required including auger drilling and/or RC drilling.

Work programme and Next Steps

HOR has planned the following activities to further investigate the surface materials:

  • Additional RC and/or auger drilling of the North Dump, Southern Dump, Gold stockpiles, C20 stockpile and Low-grade Cu sulphide stockpile located on top of the North West dump.
  • Auger drilling of the gold and copper rehandle areas
  • Acid leaching test work on oxide copper stockpiles and targets
  • Gravity recovery test work on Copper Flotation and CIP tailings
  • Assessment of the potential to recover high grade chalcocite and covellite DSO remnant from the historic mining phases via scavenging and/or heavy media separation.

For additional background on the Horseshoe Lights Project please refer to ASX releases:

12/09/2018

"Exploration Update- Horseshoe Lights Project"

06/08/2021

"Horseshoe Lights Exploration Activities Update"

10/09/2021

"Horseshoe Lights Phase 1 Auger Programme Completed"

13/09/2021

"Horseshoe Lights Phase 1 RC Drilling Programme Completed"

29/10/2021

"Horseshoe Lights RC Drilling Results"

personal

"Horseshoe Lights Phase 1 Stockpile Results Received"

26/11/2021

21/02/2022

"Horseshoe Metals Successful Relisting"

03/03/2022

"Horseshoe Lights Activities Update"

11/03/2022

"Horseshoe Lights Copper-Gold Resource Grade-Tonnage Review"

The Board of Directors of HOR has authorised this announcement to be given to the ASX.

For

- ENDS -

Enquiries

Craig Hall

Sam Burns

Non-Executive Director

Six Degrees Investor Relations

T +61 (0) 417 093 256

T +61 (0) 400 164 067

E: info@horseshoemetals.com.au

r personal use only

Figure 1 - Surface Stockpile and Dump Locations

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Horseshoe Metals Limited published this content on 17 March 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 17 March 2022 23:20:10 UTC.