IMPACT Silver Corp. provided a corporate update on the Company's recently acquired, high-grade Plomosas zinc-lead-silver mine located in Chihuahua State, Mexico. Following the completion of the Plomosas mine acquisition, the Company immediately commenced an extensive program at site to revitalize and upgrade operations and equipment, and bring on new technical and supervisory staff.

Planned upgrades will allow for an expansion of production and an aggressive exploration program has been prepared to potentially grow the size of the existing resource. Mine, Mill and Plant: The Company expects to initially restart production in 2H/2023 at levels that allow management to consider further modifications and efficiencies, where required. More meaningful production levels approaching design capacity as well as associated revenue is expected in 1H/2024.

Mine planning and rehabilitation have been ongoing while the Company replaces and repairs underground equipment including scooptrams and underground trucks. The Company is in the process of replacing mill foundations while upgrading the ball mill, conveyor and crushing systems, and flotation cells. Design capacity of the mill is 150 tpd with plans to expand.

Plans are in place to expand the existing tailings pond and concurrently, a new larger tailings pond is in the design and permitting stages. These efforts will provide some additional capacity to reestablish and grow output at the mill in the near-term, while providing the Company with substantial tailings capacity for future production increases. Substantial cost saving options are potentially available to the Company as management considers alternate electric power options as well as various changes in mining methods and mineral processing technologies.

Exploration: The Company is preparing stations for an underground drill program in the mine and drilling permits have been submitted for the upcoming surface program. One Company-owned surface drill rig has arrived on site, and a second (underground) rig is currently being manufactured and is expected to be delivered mid-summer.