METALLICA MINERALS LIMITED | ASX:MLM

QUARTERLY REPORT

MARCH 2023

Metallica Minerals Quarterly Report

ASX

RELEASE

31 March 2023

Quarterly Report

21 April 2023

Metallica Minerals is an Australian development company focussed on delivering high purity silica sand to a diversified global customer-base.

ASX: MLM

Metallica Minerals Limited (ASX: MLM) ("Metallica", "the Company") is pleased to present its activities report for the quarterly period ending 31 March 2023.

Directors

Theo Psaros Executive Chairman

Brad Sampson Non-Executive Director

Mark Bojanjac Non-Executive Director

Senior Management

Scott Waddell

CFO & Company Secretary

Nicholas Villa

GM Cape Flattery Silica Sand Project

Sam Fisher

GM Commercial

CORPORATE

AS AT 31 MARCH 2023

Issued Capital

956,898,922 Ordinary Shares

179,630,557 Listed Options

21,700,000 Unlisted Options

Shareholders

1,472 shareholders

Top 20 shareholders hold 67%

Largest Shareholders

Ilwella Pty Ltd - 24.2%

Sibelco Asia Pacific Pty Ltd - 15.1% Sparta AG - 9.6%

Cash Balance

As at 31/3/2023, MLM's cash balance was approximately $9.6m

Website

metallicaminerals.com.au

Click here to view a short video presentation on our Cape Flattery Project.

2

HIGHLIGHTS

1.

2.

3.

Maiden Inferred

Progress on DFS for

Meetings held with

Resource of 12Mt for

Silica Sand Project

various potential offtake

CFS West Project

customers and investors

(see page 7)

4.

5.

Extraordinary General

$9.6 million in cash is

Meeting held with all

available at quarter end,

resolutions passed on

with no debt

a poll

6.

CFS deemed a Controlled Action by the Federal Government

Metallica Minerals Quarterly Report

DEVELOPMENT & EXPLORATION CAPE FLATTERY SILICA SANDS

MLM

Interest

100%

The Cape Flattery Silica Project is adjacent to the

Environmental Studies

world class Cape Flattery Silica Sand mining and

The Company, along with our external environmental

shipping operation owned by Mitsubishi.

During the March 2023 quarter, the Company

consultants, have completed an array of

environmental studies at the CFS project. These

continued to advance through numerous studies,

studies have included soil sampling, ecological

approval processes and stakeholder engagement

studies and water monitoring.

activities that are all key components of our project

The lodgement of the Environmental Application

development for the Cape Flattery Silica Sand Project.

and Progressive Rehabilitation and Closure

Definitive Feasibility Study underway

Plan (PRCP) with Queensland Department of

Environment and Science (DES) has been delayed

The Definitive Feasibility Study (DFS) is underway

while the Company waits to receive the Terms of

Reference from the DCCEEW.

and remains on track for completion in 2023.

Key study areas progressed during the March

Traditional Landowner update

Quarter include continued investigation of

transhipping operations, transhipping vessel

To date, six meetings have been held with the

selection and location of key project infrastructure.

negotiation representatives of the clans who are the

traditional landowners of the planned Mining Lease

Federal Environmental Approval process

Application (MLA) area. The Company has met with

the Dingaal and Nguurruumungu representatives

During the December 2022 quarter the Company

and their respective legal advisors and the

negotiations are continuing.

submitted a Referral under the Environment

Protection and Biodiversity Conservation Act 1999

In January 2023, the Company presented the project

(EPBC Act) for the Cape Flattery Silica Sand Project.

to the Board of Directors of Hopevale Congress

The Federal Department of Climate Change, Energy,

Aboriginal Corporation (Trustee Landowner). The

meeting was the first formal presentation with

the Environment and Water (DCCEEW) assessed the

Hopevale Congress since the appointment of a new

Referral and 18 January 2023 determined that the

Board of Directors and legal representative.

CFS project is a Controlled Action under Section 75

of the EPBC Act requiring assessment and approval

Importantly, the negotiations have been held in a

under the EPBC Act prior to final approval.

professional and respectful manner with significant

On 20 February 2023, DCCEEW announced that the

information on the project being shared with the

negotiating parties from each clan. Executive

assessment will be through an Environmental Impact

Chairman Theo Psaros met with representatives

Statement (EIS).

of the Dingaal and Nguurruumungu in April 2023.

A Terms of Reference document will be issued by

Negotiations are planned to resume in late June,

DCCEEW and this will outline the additional studies

early July 2023.

to be undertaken. To date significant environmental

studies have been undertaken which will be used

towards the requirements for the EIS.

4

Metallica Minerals Quarterly Report

EPM 25734

LEGEND

Cape Flattery land mass

MLA

Coral Sea

EPM - Metallica Minerals

Mine Lease Area

ML - Mitsubishi Corporation

Cape Flattery Port limit

Metallica Minerals -

Cape Flattery Port limit

proposed export solution

Mitsubishi Corporation -

existing maritime infrastructure

Mitsubishi Corporation - existing

airport (private)

Roads

1 km

Figure 1: Metallica Minerals' CFS EPM 25734 & MLA location adjacent to the Cape Flattery Port Limit and proximity of MLA area to the planned purpose-built jetty

Purpose-built Jetty Development Application

A Development Application (DA) to the Queensland Government is being finalised for approval for the construction of a purpose-built jetty for the CFS Project.

On 13 September 2022, the Company received a letter from Department of Resources (DoR) clarifying the approvals pathway for port operations associated with existing or future silica project proposals on Cape York. The letter advises that investigations have not identified an approvals pathway for port operations proposed outside

of existing port areas and are subject to the Sustainable Ports Act 2015.

The planned jetty is located within the Cape Flattery Port limit (see Figure 1). The Cape Flattery Port is already in operation, loading silica sand onto ships for export and is an area with existing approval for marine operations.

The Jetty Development Application process has required engagement with a number of Queensland Government departments as well as the Hopevale Aboriginal Shire Council and Cook Shire Council. The DA is expected to be lodged in Q3.

Potential Offtake partners

In August 2022, the Company announced it had signed a Memorandum of Understand (MoU) with Mitsui & Co., Limited who is one of the largest global trading and investment companies based in Japan.

In January 2023, the Company completed a site visit by helicopter with potential international customers. Kenneth McLean, Chairman of Walmbaar Aboriginal Corporation accompanied the group and was able to discuss the positive impacts the project will have on the local communities.

In February and March 2023, Executive Chairman Theo Psaros travelled to Tokyo, Kuala Lumpur and London to progress discussions with potential investors and off-take partners. Further visits are planned with potential investors and off-take partners in Q2 2023.

5

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Metallica Minerals Limited published this content on 21 April 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 21 April 2023 00:09:03 UTC.