METALLICA MINERALS LIMITED | ASX:MLM

QUARTERLY REPORT

SEPTEMBER 2022

Metallica Minerals Quarterly Report

ASX

RELEASE

30 September 2022 Quarterly Report

18 October 2022

Metallica Minerals is an Australian development company focused on delivering high purity silica sand to a diversified global customer-base.

ASX: MLM

Metallica Minerals Limited (ASX: MLM) ("Metallica", "the Company") is pleased to present its activities report for the quarterly period ending 30 September 2022.

Directors

Theo Psaros Executive Chairman

Brad Sampson Non-Executive Director

Mark Bojanjac Non-Executive Director

Senior Management

Scott Waddell CFO & Company Secretary

Nicholas Villa General Manager,

Cape Flattery Silica Sand Project

CORPORATE

AS AT 30 SEPTEMBER 2022

Issued Capital

670,699,701 Ordinary Shares

179,630,557 Listed Options

19,000,000 Unlisted Options

Shareholders

1,450 shareholders

Top 20 shareholders hold 57.1%

Largest Shareholders

Ilwella Pty Ltd - 22.6%

SpartagAG - 9.7%

Dostal Nominees Pty Ltd - 6.1%

Rookharp Capital - 2.6%

Sibelco Asia Pacific Pty Ltd - 2.4%

Cash Balance

As at 30/09/2022, MLM's cash balance was approximately $3.6m

Website

metallicaminerals.com.au

A short video presentation on our Cape Flattery Project is available on our website.

2

KEY EVENTS

Queensland Government confirms Cape Flattery Silica (CFS) Project falls within Cape Flattery Port Area

JukesTodd appointed as Study Manager for the CFS Project

$3.6 million in cash is available at quarter end, with no debt

Drilling completed at the Western Areas and intersects high purity silica

Progressive rehabilitation Closure Plan (PRCP) Community Consultation completed for the CFS Project

Memorandum of Understanding signed to progress off-take agreement with Mitsui on the CFS Project

Full year statutory accounts and Annual Report lodged

Metallica Minerals Quarterly Report

DEVELOPMENT & EXPLORATION CAPE FLATTERY SILICA SANDS

MLM

Interest

100%

The Cape Flattery Silica Project is adjacent to the

Environmental Studies

world class Cape Flattery Silica Sand mining and

The Company, along with our external environmental

shipping operation owned by Mitsubishi.

During the September 2022 quarter, the Company

consultants, have completed an array of

environmental studies at the CFS project. These

continued to advance through numerous studies,

studies have included soil sampling, ecological

approval processes and stakeholder engagement

studies and water monitoring.

activities that are all key components of our project

The company is planning to lodge a Referral

development for the Cape Flattery Silica Sand

Project. In particular, there has been significant

Application for the CFS Project to the Australian

progress on the preparation of Federal and State

Government's Department of Climate Change,

environmental applications.

Energy the Environment and Water. This is due

 

to occur in Q4 2022.

Definitive Feasibility Study underway

The Environmental Application is now planned to

The Definitive Feasibility Study (DFS) is underway

be lodged in Q4 of this year to the Queensland

Department of Environment & Science (DES).

and is planned for completion in mid 2023.

The Company also plans to lodge a Progressive

JukesTodd has been appointed as the Study

Rehabilitation and Closure Plan (PRCP) with DES.

Manager for the DFS. The study will include the

The PRCP will outline how rehabilitation will be

design, engineering and planned delivery of the

undertaken progressively throughout the life of

Cape Flattery Silica operation producing 1.35Mt of

the project and what work will be undertaken

high-purity silica sand per annum.

when the project is completed. The roadshow to

The DFS team visited the Cape Flattery site in early

representatives of Dingaal and Nguurruumungu

clans, local councils and other key stakeholders to

September to inspect the project location.

inform them of the PRCP and seek feedback was

 
 

completed in September 2022. The feedback from

 

all parties remains positive.

L-R: Boyd Dale and David Bainbridge (JukesTodd), Tycho Buningh (Royal HaskoningDHV), Shailand Deeral- Rosendale (Walmbaar) and Nicholas Villa on-site at Cape Flattery

4

Metallica Minerals Quarterly Report

L-R John Deeral, Raynard Baru, Shailand Deeral-Rosendale, Stanton Thompson, Nicholas Villa (General Manger), Theo Psaros (Chairman), Tayna Yoren, Fabian O'Burns and Kenneth McLean - Dingall Clan representatives.

Traditional Landowner update

To date, four meetings have been held with the Negotiation representatives of the clans who are the traditional landowners of the planned Mining Lease Application (MLA) area. The Company has met with the Dingaal and Nguurruumungu representatives and their respective legal advisors and the negotiations are continuing.

In August 2022, the Company welcomed seven members of the Dingaal Clan to our Brisbane office to meet with our staff and introduce them to the Definitive Feasibility Study group. Chairman, Kenneth McLean addressed the group and discussed the importance of country and other Cultural Heritage matters.

Importantly, the negotiations have been held in a professional and respectful manner with significant information on the project being shared with the negotiating parties from each clan.

Purpose-built Jetty Development Application

A Development Application (DA) to the Queensland Government is being finalised for approval for the construction of a purpose-built jetty for the CFS Project.

On 13 September 2022, the Company received a letter from Department of Resources (DoR) clarifying the approvals pathway for port operations associated with existing or future silica project proposals on Cape York.

The planned jetty is located within the Cape Flattery Port limit (see Figure 1 below). The Cape Flattery Port is already in operation, loading silica sand onto ships for export and is an area with existing approval for marine operations such as being contemplated by the Company.

The Jetty Development Application process has required engagement with a number of Queensland Government departments as well as the Hope Vale Aboriginal Shire Council and Cook Shire Council. The DA is expected to be lodged in Q4 of this year.

Potential Offtake partners

In August 2022, the Company announced it had signed a Memorandum of Understand MoU with Mitsui & Co., Limited (Mitsui), Mitsui is one of the largest global trading and investment companies based in Japan.

5

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Metallica Minerals Limited published this content on 18 October 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 18 October 2022 04:02:03 UTC.