Pangolin Diamonds Corp. update shareholders on recent activities at its various projects in the Republic of Botswana, Africa. Highlights Include: All field teams fully operational; Approval granted to proceed with AK10 kimberlite 500 tonne bulk sample; New kimberlite drill targets to be delineated at Malatswae and Motloutse Projects; KW04-C dyke to be tested for macrodiamonds at Kweneng Project. AK10 Kimberlite Pipe: Approval has been granted by the Department of Mines (DoM) to Makunwu Civil Blasting (Pty) Limited, Pangolin’s JV partner on the AK10 kimberlite to proceed with the 500 tonne bulk sample. The bulk sample will be extracted from underground and access will be via a vertical shaft. Operations ceased when kimberlite was intersected at a depth of 13 metres. The shaft will be extended to a depth of approximately 32 metres from surface. At the 15, 20, 25 and 30 metre levels respectively, four horizontal drifts will be excavated to a maximum distance of 5 metres in each of the four shaft wall directions.