Po Valley Energy Limited announced it is on track for first gas from the Podere Maiar well in Italy's Selva Malvezzi gas field after ISMEA accepted the Company's application to land titles for the well site, subject to finance. Po Valley received an official letter from the General Director of Italy's ISMEA accepting its application for the land as well as services for the gas pipeline and associated cables. Payment to secure the land rights is on budget and is being processed immediately (19th September 2022).

Once ISMEA confirm the title, Po Valley will have complete access and control over the land required to construct its gas treatment plant and pipeline at the Podere Maiar-1 well site. In addition, the steel pipe has arrived on site and is being stored in readiness for construction of the 1km gas pipeline that connects the Podere Maiar-1 well to the National Gas Grid. Po Valley continues to progress its application to UNMIG/Fire Dept for approval for its operations, and plans to request UNMIG approval to commence preliminary works on the well site.