SPML House, Plot No.65 Sector-32, Gurgaon-122001

SPML PRESS RELEASE Tel: 0124-3838300

For Immediate Release Email: corpcomm@spml.co.in

SPML Infra Received New Orders of INR 642 Crore for Irrigation Project in Gujarat & Madhya Pradesh, Water Supply Scheme in Jharkhand & Power Infra Development in West Bengal Gurgaon, 21 June 2017

SPML Infra Limited has received new orders for Water Supply and Irrigation Projects in Gujarat, Madhya Pradesh and Jharkhand and Power Infra Development in West Bengal.

  • INR 500.14 Crore order from UND Irrigation Division, Jamnagar, Gujarat for Water Irrigation Project, SAUNI Yojana

  • INR 53.58 Crore order from Jharkhand Urban Infrastructure Development Corporation Ltd. for Augmentation and Strengthening of Giridih Water Supply Scheme

  • INR 45.64 Crore order from Narmada, Water Resources, Water Supply & Kalpsar Department, Gujarat for Lift Irrigation Pipeline Project

  • INR 28.80 Crore order from West Bengal State Electricity Transmission Company Limited for Construction of 132/33 kV GIS Substation at Burdwan

  • INR 13.50 Crore order from Narmada Valley Development Authority, Madhya Pradesh for Construction of Right Bank Piped Canal of Upper Beda Dam

The first order of INR 500.14 Crore of Link 1, Package IV is part of the Phase II of Saurashtra- Narmada Avtaran Irrigation; an ambitious project initiated by the Govt. of Gujarat to divert one million acre feet (1 MAF) water of Narmada Dam to 115 Reservoirs through 1115 kilometer pipeline network to irrigate 1.8 million hectare of land in Saurashtra, Kutch and north Gujarat; benefiting millions of farmers. The project also envisages supplying potable water to 39 million people across 132 towns and 11,456 villages in Gujarat to address the scarcity of drinking water. The scope of this project includes laying of 36.6 kms MS Pipeline of 3000 mm diameter of 17.5 mm thickness with external 3LPE coating & internal food grade epoxy coating; 14.17 Cumecs Pumping Station at 49 meter head and allied works. The project completion period is 24 months thereafter 10 years of O&M.

The second order of INR 53.58 Crore is for augmentation and strengthening of Giridih water supply scheme under Giridih Nagar Parishad in Jharkhand with design and construction of 7.50 lakh litre elevated service reservoir, distribution network, installation of bulk flow meters, gensets, SCADA system etc. The project completion period is 24 months along with 5 years of O&M.

The third order of INR 45.64 Crore is for lift irrigation pipeline project for transmission of 50 cusecs of water from Ch. 13900 on existing MS pipeline in Bhasariya, district Mehasana, Gujarat to

augment various reservoirs of the region by pipeline or feeder canals. The project completion period is 12 months.

The fourth order of INR 28.80 Crore is for supply, erection, testing and commissioning of 132/33 Kv GIS Substation along with 2 nos 132 Kv line bays and associated work at Burdwan in West Bengal. The project will be completed in 18 months' time.

The fifth order of INR 13.50 Crore is for construction of Right Bank Piped Canal of Existing Upper Beda Dam on turnkey basis to supply 0.735 Cumec water for irrigation in 1829 hectare cultivable command area, construction of multiple outlets for domestic raw water requirements and all other miscellaneous work related to entire system. The project completion period is 24 months along with 12 months of O&M.

Mr. Subhash Sethi, Chairman, SPML Infra, commented, "We convey our deep gratitude to Govt. of Gujarat for reposing faith on us and our execution capabilities with the new order after the successful completion of earlier project under phase 1 of SAUNI Yojana that was inaugurated by Hon'ble Prime Minister, Shri Narendra Modi ji in the presence of Shri Vijay Rupani Ji, Hon'ble Chief Minister of Gujarat last month. Our team are excited with the new order as the expertise we developed while executing the earlier order will be immensely useful. The irrigation project in Gujarat & Madhya Pradesh is to increase agriculture produce and improve the living standard of farmers in the project area by constructing irrigation canal system utilizing limited water resources efficiently to ensure equitable and assured water supply to the designed area.

SPML Infra is executing good numbers of water supply & distribution projects and our expertise in developing strong and sustainable infrastructure for water supply schemes is recognized with new order from Jharkhand. We expect more such orders as SPML will be playing an important role in this sector by making drinking water accessible to people across the country to improve the living standards. Our power transmission & distribution division is getting projects on a regular basis form different states including West Bengal. With the strong execution capabilities, we are confident to deliver these projects on time to the complete satisfaction of our esteemed clients."

About SPML Infra Ltd.:

SPML Infra is a leading infrastructure development company of India. With over three decades of experience, it has executed more than 600 projects and created significant value for our country that have touched the lives of millions of people; be it provision of drinking water, improved sewerage facilities, better municipal waste management, building roads and highways and lighting up homes. SPML has established its leadership in urban infrastructure development on EPC, PPP and BOOT basis.

SPML - Subhash Projects & Marketing Ltd. published this content on 21 June 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 21 June 2017 05:25:04 UTC.

Original documenthttp://www.spml.co.in/downloads/2017/SPML-Infra-Secures-New-Orders-of-INR-642-Crore.pdf

Public permalinkhttp://www.publicnow.com/view/3F2032DF310B2D982160D3F8E47823E1FE2746D1