Symbol Mining Limited provide an operational update for the Macy Zn-Pb mine in Nigeria. The Company can confirm the commissioning of the second wash plant at the Macy Mine is now completed with a combined concentrate production from both wash plants of 100 tonnes per day has been achieved over a 6-day period. On this basis the combined processing plants have demonstrated the capability to achieve 3,000 tonnes of zinc concentrate per month. The second wash plant is a much larger unit, which has been optimally designed with several modifications identified from the pilot wash plant, improving material handling and ability to increase zinc concentrate production. The completion date had been delayed by several weeks due to the vendor rectifying minor mechanical defects before hand-over. The Macy operational team is now implementing further improvements to increase the wash plants performance, which can be reflected with a record daily production of 136t @ 42% zinc concentrates during the previous week.