Tulla Resources Plc provided an update of project construction and mining activities at the Norseman Gold Project (TUL 50%). Construction of the new 1 million tonne per annum processing plant has continued to progress as planned despite numerous COVID-19 cases on site during the past quarter. The Manager and GR Engineering site personnel have managed the challenges presented to date superbly, and completion is still expected during August.

The project has been aided by the early procurement of all processing plant components during the approvals process, both expediting construction times and insulating the Joint Venture from the significant cost pressures now generally seen in the construction industry. Ancillary works including the power station upgrade, tailing storage facility expansion and bore field re-instatement are also continuing in line with the project schedule. Hampton Mining & Civil have successfully ramped up operations at the Scotia Mining Centre with clearing and other preparation works completed and primary mining activities well underway.

Large scale grade control drilling programs are also ongoing at Green Lantern. Results to date have validated the Mineral Resource model with multiple zones of thick and often high grade mineralisation noted. In addition to mining operations being underway, the Joint Venture has continued to drill out the Green Lantern stage two mineralisation.

An updated Mineral Resource and Ore Reserve is expected to be completed in the coming weeks. WestAuz Mining has commenced underground works, re-establishing services and preparing for the imminent commencement of concurrent decline rehabilitation and ore development. Ore development will commence this week, with three development jumbos to be active in the mine by August 2022.

The Company's asset is a 50% interest in the Central Norseman Gold Project (the "Project"), a historic gold province near the town of Norseman in the Goldfields of Western Australia, which commenced operations in 1935.