W Resources Plc announced it has successfully completed the construction of a new water dam at the La Parrilla mine in Spain in order to resolve the issue of the high water levels. Dewatering of the mine pit is now underway and once water levels are reduced the team will be in a position to safely regain access to high-grade ore areas. The 500,000m3 dam is receiving water from the mine pit at a rate of 2,500m3 per hour, which will enable access to the next level of fresh ore in the next few days. Construction of this dam has been hugely successful with staff and contractors working tirelessly to complete this stage of the project. The final phase of the project to provide a permanent solution to the water issues at La Parrilla, comprising of a second dam, is currently at the design stage and is expected to be completed in Fourth Quarter 2021.