CuDeco Limited announced production results for the October 2017. The company reported that October production at its Rocklands Copper Mine in Cloncurry Queensland included 1,759 tonnes of copper metal produced in 7,475 DMT of concentrate averaging 23.54% Cu (mill estimates). October production is an improvement on September of 1,707 DMT of copper metal produced. Metal recovery in October was 87.9% compared to 89.8% in September. The minor reduction is due to the effects of start-stop inefficiencies on grinding due to periods of shut-down. Overall performance in October was lower than forecast partially due to an unplanned maintenance shut- down period to address issues related to the previous months bearing change-out in the main ball mill motor. This contributed to mill throughput being circa 30% lower than forecast for the period. Approximately 1.82 million DMT of rock was mined in October from the LM2 (0.51Mt), RS1 (0.84Mt) and LM3 (0.47Mt) pits, bringing the total since mining recommenced in March 2017 to 9.3 million DMT of rock. Ore mined in October was 294,302 DMT @ 1.35% Cu. Total ore mined since March is 2,116,366 @ 1.13% Cu at a strip ratio of circa 2.8 to 1.