Empire Oil & Gas NL provided the update on the Red Gully North-1 (RGN-1) project. The original plan was to remove the two packers covering the C and Upper D sands in one run however, this could not be achieved. The upper completion packer was cut and successfully retrieved from the wellbore. The second packer assembly was latched and pulled 20 metres before becoming stuck in the hole at the bottom of the C sand perforations. The current assumption is that compacted shale/sand from the C sand perforations have wedged in the narrow clearance between the casing and the unset packer. A wash over tool was run to circulate out the shale/sand formation material and evidence of debris was seen at surface. The fishing string is currently being rerun to remove the second packer from the hole. The completion packer removal issues have extended the planned remediation by approximately 8 days. The current plan is to: Remove the second packer assembly from the well to allow access to both the C and Upper D perforations; Install bridge plugs/retainers and perform two remedial cementing operations. Run cement bond logs to evaluate cement integrity; Clean-out well, re-perforate and run new two zone isolation completion; Test well after de-mobilising the workover rig.