Integrated Green Energy Solutions Ltd. announced that onsite construction in Amsterdam is progressing according to schedule with the focus currently on civil works. In the last week, steel mesh and concrete reinforcement bars have been successfully installed. Precise positioning of these reinforcements during concrete placement is critical to the structure's performance, as it provides the structural integrity and strength to support the incoming end of life plastic to fuel modules and associated buildings. Stage 1 pouring of the concrete slab around the production area will be finalized by the first week of March. Upon completion of this significant phase of construction, it is anticipated that construction will progress rapidly. The curing of the concrete to full strength will take approximately 28 days. This is however a progressive process with the portion of the concrete slab required to support the first module being of sufficient strength to take this load within 21 days.