Nevada Copper Corp. provided updates on restart activities at its Pumpkin Hollow underground mine (the "Underground Mine"). U unexpected bottlenecks encountered in process plant systems are being mitigated.

Third ore pass and temporary use of ore bin from new life-of-mine ("LOM") ore handling system provides material handling capacity to meet plan until underground crusher is installed. Paste plant fully commissioned. Life of Mine Infrastructure.

In addition to the completion and commissioning of the Geho dewatering system and the second phase of the ore handling system, other LOM infrastructure improvements include the drilling of a new fuel delivery hole, drilling of a second paste hole that will provide LOM paste delivery for EN Zone stopes and improvements to the water infiltration system on surface to handle excess surge capacity. A scope of work is being issued to potential contractors for the final phase of the ore handling system., which includes installation and commissioning of the crushing system.