Oil & Gas Development Company Limited has successfully completed the Khewari (Suleman 1 & 2) Development Project, with potential gas production of 10 million standard cubic feet per day (MMSCFD). Currently, 7 MMSCFD of gas is being processed at the Sinjhoro Plant in the Sanghar District, Sindh Province, and will be ramped up to the full potential. The wells are under choke optimization process for further enhancement in gas supply.

OGDCL adopted a fast-track strategy, accelerating processes for the first gas injection by laying a 6-inch diameter pipeline spanning 14.5 kilometers from the Gathering Facility near Suleman-1 to the Chabaro Tie-in point. The venture is a collaborative effort in which OGDCL serves as the operator with a 77.50% stake, while Government Holdings Private Limited (GHPL) holds the 22.50% share.