Alara Resources Limited update investors on significant progress in the construction phase of the Al Wash-hi Majaza Copper-Gold Project (Project) in that country. The Company maintains the expectation that Project commissioning will occur early in the June 2023 quarter. The following photos show construction progress in detail.

Key activities underway include electrical work currently being undertaken at the primary substation. The handover date for this integral part of the mine's infrastructure is 25 December 2022. Other works-related focus areas by AHRL over October/November included the erection of major retaining walls, a number of foundation laying tasks (specifically for SAG, regrind and ball mill, flotation cell, reagent tank and tailings filter tank) and copper concentrate thickener erection works.