Alara Resources Limited provided an update on its project development activities at the Al Wash-hi Majaza Copper-Gold Project (Project) in that country. Alara owns a 51% equity interest in the Al Hadeetha Resources LLC (AHRL) joint venture which is developing the Project. On-site construction works at the Project have continued to ramp up.

Construction work is underway on the primary crushing building, the grinding area and electrical rooms. Work progressed despite unusually heavy rain over July causing a short delay, as some dewatering of excavated pits, cleaning and rework activities was undertaken. The Mining Plan for the Year 0 area is currently being executed. Pre stripping mining started on 1 February 2022 in this area.

Key mine development work including the haul road, drainage channels, settling ponds, topsoil stacking, waste dump and ROM pad have already been completed. Presently, the Mine workings of between 450 mRL and 440 mRL is in progress. The ultimate floor level at the end of the pre-stripping period is proposed at 410 mRL.

The ramp designing to reach up to 410 mRL is now in progress. AHRL regularly checks and demarcates blast areas and as part of drilling operations supervision. Average drill length and drill cuttings generated are also checked at the site.

Vibration and noise level data generated during each blast are recorded and compiled. This data indicates that vibration and noise levels occurring to date during the blasting are within permissible limits. A topographic survey is being carried out by Gulf Testing Solutions.

A volumetric calculation for excavated areas is conducted each month. The excavation quantities are reported monthly on a per-trip basis. These quantities are reconciled each quarter with the topographic survey excavated volume.