GE Power India Limited has received a LOA from Sanjay Gandhi Thermal Power Station, MP Power Generating Co. Ltd. (MPPGCL), details of which are mentioned below:- Significant terms and conditions of order(s)/contract(s) awarded in brief: LOA for Design, Engineering, Supply of Wind Box casing with buck stay, bracings etc. along with modified air register and dismantling of existing system and Erection of wind box along with modified air register in unit No 1 of 210 MW ABL make boilers of PH-1, SGTPS, MPPGCL Birsinghpur Time period by which the order(s)/contract(s) is to be executed: 180 Days for Supply+ 35 days for service.

Broad consideration or size of the order(s)/contract(s): Base value as INR 700.1 million plus (GST 18%).